If equipped with pneumatic carriage

-press the pneumatic switch on the pneumatic carriage, lift approximately 300mm.

- press the other side of pneumatic lift the safety rod of rolling jack, lower the rolling jack.

-press the other side of pneumatic pump, verify the insurance instruction.

If equipped with electrical carriage.

-turn the selector switch to “rolling jack” position.

-press “up” button SB1, lift approximately 300mm.

-press “down” button SB2 and lift the safety rod of rolling jack, lower the rolling jack.

-press “down” button SB2, verify the safety instruction is reliable.

Electrical rolling jack limit adjustment

-clicking “up” button SB1, lift approximately 370mm.

-adjust the process of limit switch SQ.

-clicking the procedure of lifting verity the accuracy of rolling jack.

Anchor bolts installation

-affix the lift to the concrete base with 16 anchor bolts using a percussion drill into 120mm.

-At first, no expansion bolts are installed.

Level adjustment

-adjust the level of the two front turntable and the slide plates on both sides at back.